The Kinfields Village Stage 2 team has been named a finalist for the Veros Best Team Award at the 2026 Central Property People Awards.

Led by owner Kirkdale Investments, the multidisciplinary team reshaped a consented two-storey retail and office development in response to changing market demand. By connecting leasing, design, planning, engineering and construction advice, the team kept the project moving and delivered a fully leased extension of Kinfields Village in Rototuna, Hamilton.

The team brought together APG Architects, BCD Group, Fluid Engineering, Fosters, Lodge Real Estate, Tonkin + Taylor and Veros. The recognition reflects how the organisations worked across traditional discipline boundaries and remained involved until the new businesses were operating.

Why the original development plan changed

The original consent provided for a two-storey retail and office development. As leasing progressed, however, the market was showing stronger demand for retail space and insufficient demand for the proposed offices.

Continuing with the consented design would have increased Kirkdale’s leasing exposure. Stopping for a complete redesign risked losing early tenant interest and missing the summer earthworks window.

Instead, the team considered the commercial and technical issues together.

Lodge Real Estate provided current evidence on tenant demand and rental levels. APG Architects tested a single-storey retail design that retained the character of the wider village. Fosters contributed pricing, buildability and programme advice through Early Contractor Involvement, while Tonkin + Taylor, BCD Group and Fluid Engineering worked through the planning, structural, geotechnical and building-services implications.

Veros coordinated the development response and consolidated the advice so Kirkdale could understand the cost, programme, leasing and technical consequences before making each key decision.

The result was a commercially viable single-storey development that could keep moving without compromising the quality expected of an asset intended for long-term ownership.

How the team kept the project moving

One of the most important decisions was to begin ground remediation before every aspect of the revised design and consent variation had been finalised.

With the likely building footprint understood, the team identified the work that could proceed with confidence. This protected the summer earthworks programme while the remaining design and consenting matters continued.

It was a measured decision grounded in knowledge of the site, clear technical advice and established working relationships. Issues were raised early, the right disciplines were brought into the conversation, and decisions were made with a clear understanding of their wider consequences.

What Kinfields Village Stage 2 delivered

The base build was delivered three weeks ahead of programme and slightly under the revised single-storey budget. All nine units had lease commitments by base-build completion, and eight businesses were operating across the development by late 2025.

For Kirkdale Investments, the outcome was a viable, fully leased asset designed for long-term ownership. For Rototuna, Stage 2 broadened the mix of hospitality, health, fitness, personal and professional services available within the village.

The Central Property People Awards will be presented at Wintec in Hamilton on 22 October 2026.

Read more about the Kinfields Village project and see how Veros has supported Kirkdale Investments from commercial strategy through to delivery.